Italy set to spearhead floating wind in southern Europe | Reuters Occasions

Italy is poised to change into a number one floating wind market nevertheless it should swiftly implement new regulation and grid plans, builders stated.

Associated Articles




Floating wind exercise is ramping up in Italy, boosted by new regulation that helps large-scale deployment.

A draft market framework printed by the federal government in March units out value help mechanisms and three.5 GW of offshore wind energy auctions between 2023 and 2026. The European Union has raised renewable vitality targets following Russia’s invasion of Ukraine however Italy’s response stays unsure following the collapse of Prime Minister Mario Draghi’s authorities earlier this month.

In the meantime, Italian developer Renexia has accomplished the nation’s first utility-scale offshore wind farm off the coast of Taranto, Apulia and goals to construct the 1 GW Med Wind floating wind farm within the Strait of Sicily by 2025.

The 30 MW Taranto challenge makes use of fixed-bottom expertise however most of Italy’s bigger offshore wind tasks can be sited in deeper waters the place wind sources are greater, requiring floating constructions. Transmission operator Terna has obtained 70 GW of offshore wind proposals and builders embody a partnership between Falck Renewables and BlueFloat Vitality and a consortium together with Eni and Copenhagen Infrastructure Companions (CIP). Most tasks are off the coasts of Sardinia and Sicily and within the Adriatic and Higher Tyrrhenian seas.

             Italy’s energy era by supply

                                   (Click on picture to enlarge)

Supply: Worldwide Vitality Company (IEA)

The tempo of floating wind deployment will largely rely on Italy’s new mechanisms for value help, allowing and grid connections, builders informed Reuters Occasions. Challenge companions hope the brand new rules can be applied this yr and the primary auctions held in 2023.

Grid operator Terna is drawing up plans for 22 GW of offshore wind connections and well timed grid construct may place Italy on the forefront of offshore wind building in southern Europe and amongst Europe’s main floating wind markets.

Worth help

A number of different European international locations are accelerating floating wind deployment however most exercise is within the Atlantic and North Seas.

Up to now, tasks developed in Italy have been unsolicited. New market frameworks will present value help alongside a extra environment friendly approval course of, permitting the trade to quickly deploy at scale.

Italy is planning to implement a contract for distinction (CFD) public sale mannequin just like that utilized in UK and different components of Europe, fixing income at an agreed strike value. Floating wind prices are presently far greater than fastened backside tasks however are anticipated to fall quickly as bigger tasks carry expertise and set up learnings. Italy’s authorities proposed a value cap of 165 euros/MWh ($168.6/MWh) in its draft regulation printed in March. Business group ANEV has referred to as for the next value of 190 euro/MWh, significantly for tasks smaller than 500 MW.

                                     Wholesale energy costs in Italy 

                                                              (Click on picture to enlarge)

Supply: European Fee’s Quarterly Electrical energy Market Report 

Renexia will bid its Med Wind challenge within the first CFD public sale anticipated subsequent yr, Riccardo Toto, Normal Supervisor of the corporate, informed Reuters Occasions. Med Wind can be situated over 60 kilometres from the coast in water depths of 300-600 metres and can use the most recent large-scale 14.7 MW generators.

Italy’s draft framework requires builders to have accomplished environmental allowing to take part in CFD auctions. Renexia signed an interconnection settlement for Med Wind with Terna earlier this yr and goals to submit the environmental impression examine by October, Toto stated.

The EU has referred to as on member states to hurry up allowing of large-scale renewable vitality tasks in areas with low environmental impression. Renexia expects Italy’s Setting Ministry will take six to 12 months to finish the environmental evaluation for Med Wind and concern the ultimate allow, Toto stated.

Builders prepared

Italy’s draft framework is broadly in step with different offshore wind markets however the last model should embody capability targets alongside the mechanisms for allowing, web site allocation and grid connection, a spokesperson at Eni Plenitude, the Italian group’s renewable vitality division, stated.

Eni and companions are growing two tasks with mixed capability of 750 MW offshore Sicily and Sardinia respectively. The Sicily challenge could possibly be on-line by 2026 and Sardinia by 2028, offered auctions are swiftly applied , the spokesperson stated.

“Tariff help can be wanted for any offshore challenge to mature in Italy,” the spokesperson stated.

Grid connections are a key danger as tasks usually require onshore grid upgrades in addition to offshore infrastructure. Grid operator Terna is rolling out a huge improve of onshore infrastructure to attach up a surge in new onshore wind and photo voltaic capability within the south to greater demand centres within the north. Terna plans to take a position round 4 billion euros in southern Italy over the subsequent 5 years and a few 18 billion euros nationwide over the subsequent 10 years.

The event plans of Italian group Falck Renewables and BlueFloat Vitality present the potential for development. The businesses are collectively growing six tasks for nearly 6 GW of capability, together with three in Sardinia waters for two.4 GW, two in Puglia for two.5 GW and a 675 MW challenge in Calabria.

The timeline of the tasks will rely on the allowing and grid connection processes however the first could possibly be on-line by 2028, Ksenia Balanda, Director of Falck and BlueFloat’s floating wind tasks in Italy, informed Reuters Occasions.

The companions are presently specializing in environmental offshore research.

“To finish our challenge by 2028, we have to get the permission to construct and the grid connection approval by the [grid operator] by 2024 and full the element design and procurement by 2025,” Balanda stated.

Reporting by Neil Ford